Blogging about the Garbage Garage has connected us with amazing eco-enthusiasts around the world. Thank you for all the interest and comments.  This blog (the final on this project) will focus on the garage’s construction, the best part! See previous posts for information on Project Genesis and Design, Permitting and Preparation for Construction.

Construction Process:

The Long Way Home crew (Liz and Adam Howland, Erica Temple and Aaron Colvin) came from Guatemala to install the rammed-earth tire walls. Once permits were in hand, The Riverview Company coordinated the foundation work, including the rebar that anchored the foundation to the tire walls (and reassured the building inspector). I tried to prepare for the crew’s arrival by ordering the soil that would be used to fill the tires. My extensive research and questioning of experts was not helpful, and the soil ended up being far too sandy for the required use. Quote from Adam from Long Way Home “That’s not dirt.” Drat.

So, once the crew arrived, they had the cumbersome task of finding soil that would compact well in the tires. The selected soil ended up being a mix of sand and clay. At this point, the comparisons with construction in the US and Guatemala began. In Guatemala, there was is no special search for soil – they use what is there. Fortunately, we were able to use the sand later in the project as a base for the slab and the pavers.

Elizabeth (the owner) supplied the tires. The selection of the tires was crucial for this project since the finished exterior wall needed to be vertical and would have a stucco finish. We couldn’t have various thicknesses and widths of tires as can be used in the Guatemalan projects, where the final buildings are more organic and rough in finish. It turned out that there was some variance in the tires, but the LWH crew was expert at sorting and placing the tires accordingly.

IMG_2732

Volunteers helping with the tire-pounding

IMG_2715

Liz and Erica getting the dirt ready

As part of the permit approvals, we were required to have the compaction of the soil tested during construction.  The compaction consistently met and exceeded all requirements.  (More Guatemala comparisons…compaction testing?!)

The Riverview Company followed up with the installation of the slab, the wall, attic and roof framing above the tires, and the plywood underlayment and stucco exterior finish.  IMG_2794

Brett Belisle from Riverview working on the roof

IMG_2799

Detail of the interior

Adam from the Long Way Home came back to install the glass bottles in the upper gable, and also installed some back-lighting behind the bottle wall to light the gable at night. The glass bottles were a challenge – we all love the idea of brightly colored bottles, but we had trouble finding bottles outside of clear, brown and green. There is a certain bright blue vodka bottle that we couldn’t get enough of…LWH did have a volunteer party, where everyone could get a chance to pound tires and to donate some bottles.  I gave tire-pounding a try that day, for about a minute.  Erica and Liz are now my new heroes.

IMG_2952

Adam working on the bottle wall

DSC_0098

Final exterior

DSC_0103

Final interior

DSC_0108

Interior at the bottle wall

A recap of the project:

The genesis of this project was my client, Elizabeth Rose, who is president of Long Way Home, a community-based, nonprofit organization in Guatemala that is building homes and schools using these construction methods.  In Guatemala, these construction types are a perfect solution for very poor residents who need shelter and community buildings.  In addition to the benefits noted above, building with tires, cans and bottles is cheap; the materials are virtually free, labor costs are low, and the building techniques are easily taught to otherwise unskilled laborers.

Elizabeth saw her family’s need for a garage as an opportunity to showcase alternative environmentally sustainable building practices and to help potential supporters understand the important work that Long Way Home is doing.

We are grateful to our amazing clients (Elizabeth and her husband Joe) for the opportunity to be involved in such an interesting and important project.  We appreciate their tenacity in getting the project done and their amazing outlook even during the biggest challenges we encountered.

Let us know if you have any questions about the Garbage Garage. We had such fun being a part of the project and hope that it will stand as a demonstration of creative approaches to construction that are sensitive to the needs of communities.

With best wishes,

Juli MacDonald, GreenBridge Architects

978.518.2811  juli@greenbridgearchitects.com

 

More information:

Georgetown Record’s article via Wicked Local

Wicked Local photo gallery

Tires, Cans and Bottles, Oh My!

Tires, Cans and Bottles, Oh My! (Part 2)

It’s hard to believe that it’s been a year since we first started working on the “Garbage Garage” , a new garage constructed using rammed-earth tires and salvaged glass bottles. (see our post from June 2009)

Last month, the painters completed their work. It is done!

DSC_0098

DSC_0104

In this blog, I’ll discuss our design process and preparing for construction. Next month’s blog will be focused on the construction process.

Recap

The genesis of this project was my client, Elizabeth Rose, who is president of Long Way Home, a community-based, nonprofit organization in Guatemala that is building homes and schools using these construction methods.  In Guatemala, these construction types are a perfect solution for very poor residents who need shelter and community buildings.  In addition to the benefits noted above, building with tires, cans and bottles is cheap; the materials are virtually free, labor costs are low, and the building techniques are easily taught to otherwise unskilled laborers.

Elizabeth saw her family’s need for a garage as an opportunity to showcase alternative environmentally sustainable building practices and to help potential supporters understand the important work that Long Way Home is doing.

We are grateful to our amazing clients (Elizabeth and her husband Joe)  for the opportunity to be involved in such an interesting and important project.  We appreciate their tenacity in getting the project done and their amazing outlook even during the biggest challenges we encountered.

Construction Documentation and Planning for Construction

The project was quite a journey…we worked hard with Joe Fix, our structural engineer, on proper detailing for the project. The wall details and construction became a hybrid of the methods used by Long Way Home in Guatemala and methods traditional for this area and required for permit approval. Ericka Temple, who is part of Long Way Home, assisted with the construction drawings and was also part of the construction crew. The final design included a massive concrete foundation with steel reinforcing bars anchoring the foundation to the tire walls. Here is one of the wall details:

 rose_wall secs copy

Placing the garage on the site was another challenge. Construction of the garage would be near a beautiful cherry tree and we needed to avoid harming it during construction. We also wanted the placement to ensure that the garage was not seen first while approaching on the drive. Matt Ulrich from UBLA provided the site design work for what proved to be a perfect location for the new garage.

DSC_0109 (16)

We had some touch and go with the moving the project forward. Our first hurdle was finding a contractor comfortable working with the rammed-tire process. Our clients planned to bring a Long Way Home crew from Guatemala to complete the tire portion of the project, but contractors were still squeamish and bid the project (high) accordingly. We even had one low point in the project when our client requested that for cost reasons, we revise the drawings for conventional construction. The project lost all momentum until Elizabeth said, “Wait! What are we doing?” She really wanted the garage to be as originally conceived, a demonstration of construction using salvaged materials.

GreenBridge’s partner company, The Riverview Company, stepped up to the plate. Steven was excited to see the construction method and was comfortable working with the Long Way Home Crew. Next hurdle – permitting!

The Permit Process

When we were initially looking at the project, I spoke with the Georgetown building inspector. He was excited to work with us in the permitting process. He is also a ‘green’ builder, and we felt we had a strong advocate in the town. Once we were ready to submit for permit, we found out that he no longer worked there!! The interim inspector ended up being incredibly helpful and supportive of the project, but did request review from the state inspector and additional engineering documentation for the project.  Once we’d submitted proper engineering documentation and agreed to have the rammed earth in the tires tested for compaction throughout the construction process, the permit was approved. We obtained structural reports from EarthShip verifying the structural integrity of the rammed-earth tire walls, and we engaged McPhail and Associates to provide compaction testing.

With our soils engineer at the ready, contractor in place, and plane tickets purchased for the Long Way Home crew, we were ready for construction. Stay tuned to our next blog on construction of the Garbage Garage!

Juli MacDonald, GreenBridge Architects

978.518.2811

Georgetown Residence

November 22, 2007

a-5.jpg

GreenBridge is continuing our work on the  Georgetown Residence, refining drawings for the house addition and remodeling and gearing up for the garage design.  This is the first project of the newly created ‘green home team’ (see the Georgetown Residence Blog)….the development of our team communications and processes has been vital to our and our clients’ goals of incorporating new advanced technologies and materials into the project. 